The program in figures

100
MW
Total capacity
1100
ha
Production area
60
v
Operational lifetime
2030
Commissioning year

Information about the program

The Noste program consists of Kapusta and Vaaranlammet pumped hydro energy storage project sites, which are being developed as separate projects. The projects are moderate in scale, with planned capacity of 50-100 MW each. Each project area comprises a production area of approximately 1,100 hectares, as well as electricity transmission infrastructure required for the project.

What is pumped hydro energy storage?

The purpose of pumped hydro energy storage is to store electricity and generate electricity when supply is more limited.

The system works by releasing water from an upper reservoir through turbines into the watercourse below. Water is pumped into the upper reservoir when electricity is abundant and released to generate electricity when supply is more limited.

Why do we need pumped hydro energy storage?

The need for electricity storages and the development of balancing capacity has increased significantly in Finland in recent years, as more weather-dependent wind and solar power capacity has been built.

By balancing fluctuations in weather-dependent electricity generation, pumped hydro energy storage helps stabilize the electricity system, supports the availability of electricity and contributes to a stable operating environment for industry.

Although hydro energy storage power plants have previously been built in Finland, pumped hydro is one of the oldest methods of storing energy. Pumped-storage power plants are widely used in countries such as Norway and Austria, where geographical conditions are favorable for their development.

Why are pumped-storage power plants being planned in Kemijärvi?

Pumped-storage power plants require sufficient water resources and gross head.

Kemijärvi’s geographical conditions, extensive waterways and variations in elevation provide favorable conditions for pumped hydro energy storage. Furthermore, the area has an existing, well-developed electricity grid.

The development of the pumped hydro energy storage project in Kemijärvi has been supported by good cooperation with local landowners. The necessary land-use rights are based entirely on voluntary agreements.

How does pumped-storage power plant affect the local environment?

As with all human activity, pumped hydro energy storage projects also have an impact on the environment. However, the starting point of the planning process is to minimize any adverse environmental impacts. Pumped hydro energy storage projects are subject to a statutory EIA procedure, during which the potential impacts of the projects are assessed.

We will provide further information on the identified environmental impacts as the EIA process progresses. As part of the EIA procedure, we will assess the projects’ impacts on the following areas, among other things:

  • Water bodies

  • Fauna and flora

  • Landscape and cultural environment

  • People’s living conditions and quality of life

Further details on the environmental impact assessment of the Kapusta and Vaaranlammet pumped hydro energy storage projects can be found on the ymparisto.fi website:

Kapusta
Vaaranlammet

Significant regional economic impacts

We want to build a pumped hydro energy storage power plant in Kemijärvi that will strengthen the vitality of the region well into the future.

The construction of pumped hydro energy storage power plant will have significant positive impacts on the economy and business activity in Kemijärvi and neighboring municipalities. The project will create jobs both during construction and operation and generate municipal and real estate tax revenues for the municipality.

The two pumped hydro energy storage projects

The project consists of the Kapusta and Vaaranlammet pumped hydro energy storage power plants, which are being developed as separate projects.

The Kapusta Pumped Hydro Energy Storage Project

The Kapusta pumped hydro energy storage project is being planned for the Kapusta area in Kemijärvi, along the River Kemijoki. The project site is located approximately 34 kilometers south of the municipality center of Kemijärvi.ㅤㅤㅤ

Total capacity

50–100 MW

Gross head

70–85 m

Reservoir volume

1–1,5 GWh (10–24 h)

About the project area

The project area comprises a production area of approximately 1,100 hectares, as well as the electricity transmission infrastructure required by the project. The volume of the upper reservoir would be approximately 9 Mm³. The project is planned to be connected to the electricity grid via either the Seitakorva substation in Kemijärvi or the Pirttikoski substation in Rovaniemi. The construction period for the project is approximately 3.5 years, and the operational lifetime of the facility is approximately 60 years.

Project timeline

  • 2024 Launch of the local master planning and EIA processes

  • 2024: Beginning of environmental and ecological surveys

  • 2024 Participation and Assessment Scheme (OAS) for the Local Master Plan available for public review

  • 2025 EIA program and draft local master plan available for public review

  • 2026: Completion of the EIA report

  • 2027 Local master plan proposal and completion of the land-use planning process

  • 2027–2028 Water permit and construction permits

  • 2028 – Start of construction

  • 2030 – Commissioning in the early 2030s

The Vaaranlammet Pumped Hydro Energy Storage Project

Plans are being drawn up for the Vaaranlampi pumped-storage power station project in the lakeside area of Kemijärvi, in the Vaaranlampi area of Räisälä. The project site is situated approximately 25 kilometres south-east of the centre of Kemijärvi.

Total capacity

50–100 MW

Gross head

95–115 m

Reservoir volume

c. 2,5 GWh (10–24 h)

About the project area

The project area comprises a production area of approximately 1,100 hectares and the electricity transmission infrastructure required for the project. The volume of the upper reservoir would be approximately 12 Mm³. The project is planned to be connected to the electricity grid via either the Seitakorva substation in Kemijärvi or the Pirttikoski substation in Rovaniemi. The construction of the pumped-storage power station will take approximately 3.5 years, and the operational lifetime of the facility is approximately 60 years.

Project timeline

  • 2024–2025: Launch of the local master planning and EIA processes

  • 2025: Beginning of environmental and ecological surveys

  • 2025 Participation and Assessment Scheme (OAS) and draft local master plan available for public review

  • 2026 EIA program available for public review

  • 2027: Completion of the EIA report

  • 2027–2028 Local master plan proposal and completion of the land-use planning process

  • 2028–2029 Water permit and construction permits

  • 2029 – Start of construction

  • 2030 – Commissioning in the early 2030s

Communication with stakeholders

We want to develop the Kapusta and Vaaranlammet pumped hydro energy storage projects in collaboration with local communities and stakeholders.

We maintain an ongoing dialogue with local organisations and are open to various forms of collaboration. We are keen to hear which forms of participation and communication would best meet the needs of local stakeholders. Please feel free to get in touch

Karri Huusko

Karri Huusko

Project Development Director